Project Location
wilson, nc
Client Name
Gray Construction, Inc.
Project Value
$2,000,000
Project Completion Date
September 2020
Description
Mullins Mechanical worked with Gray Construction to provide the mechanical system installation for Bridgestone in Wilson, NC. The HVAC system included a rooftop unit with energy recovery, (2) makeup air units, (19) gas unit heaters, louvers, and exhaust fans for ventilation. The MMW team installed 19 high-volume, low speed fans for air circulation in the plant. For this project, Mullins also installed a building automation system.